Google camera apk 4.4.211/24/2023 ![]() ![]() If the timephased cumulative percent complete does not reach midnight on the day before the status date, the status field is set as Late.If the timephased cumulative percent complete is spread to at least the day before the status date, the status field is set as on schedule.If the task is 100% completed, Microsoft Project sets it as complete.This is how you can define a task status in Microsoft Project.